05.22.13

Herkimer CSD - 2007 Excel Project

Scope of Work List

Click Here to View Pictures 

Herkimer Elementary School

•   Replace Two Windows in Each Classroom of the A & B Wings
•   Replace Remaining Windows in A and B Wings
•   Improve Air Circulation/PRV
•   Replace Existing Unit Ventilators (50 Rooms)
•   Replace Roof & Skylights
•   Add Ansul Fire Suppression Gas Shut Off Valve for Kitchen Hood
•   Add Emergency Lighting & Generator (150KW) - Pumps, Security, Boilers, Phone, Kitchen Coolers & Freezers
•   Add Security System (Cameras at Entrances, Corridors)
•   Add Keyless Entrance System / Buzzer System for Front Entrance (One Door)
•   Upgrade Existing Phone System
•   Provide New PA System
•   Replace Pump at Leech Field
•   Reconstruct and Enclose Entry Canopy
•   Provide Emergency Lighting, & Security System for Parking Lots & Athletic Fields (Cameras)
•   Repair Septic System
•   Provide Air Conditioning/Ventilation for Assistant Principal's Office
•   Provide Air Conditioning/Ventilation for B20 & B21 Including Windows
•   Provide Air Conditioning for Copy Room
•   Provide Air Conditioning for Cafetorium
•   Replace Carpet in Library (Inc. Assistant Principal's Office)
•   Replace Carpet in Main Offices
•   Provide Carpet for Conference Room (Rm 142)
•   Replace Ceiling Tile & Grid in Corridors
•   Add DDC Controls for Gym
•   Provide Wireless Internet (10 Wireless Access Ports)
•   Replace Front Entrance Sidewalks/Curbs
•   Improve Drainage at Soccer Field
•   Replace Curbs at Pine Grove Road Entrance For Right Turn Only out of Entrance, Add Sign
•   Additional site work for Traffic Control at Pine Grove Entrance
•   Two (2) New Marquees - one (1) at Athletic Complex, one (1) at Rear Entrance
•   Special Ed. Conference Room / Office Addition
•   Paint Door Frames
•   Add Canopy at A Wing
•   Replace Playscape (1) & Make Handicapped Accessible


Herkimer Jr./Sr. High School

•   Complete Renovation of "Old" Toilet Rooms (upstairs & downstairs)
•   Replace Exterior Doors & Hardware
•   Install Overhead Door in Rm 153
•   Reline Chimney, Combustion Air Dampers & Bring Up to Code
•   Reconstruct "Old" Foyer
•   Replace Roof "Old" Foyer
•   Expand Existing Security System (Cameras at Entrances & Corridors)
•   Add Keyless Entrance System for Entrances and PE Room
•   Upgrade Existing Phone System
•   New Exhaust Fan for Tech Room
•   Provide Dust Collection and Fencing for Rm. 153
•   Add Door to Roof (Second Floor of Gym)
•   Reconstruct Stairway 3
•   Provide 6 Additional Data Drops in Classrooms
•   Provide Additional Power to Back of Auditorium & Relocate Sound & Lighting Systems
•   Replace Auditorium Flooring
•   Provide Aisle Lighting in Auditorium - LED strips, 6 Runs
•   Refurbish Auditorium Seating (800 seats +/-)
•   Replace Student Lockers in "Old" Building (560)
•   Provide Motorized Shades for Library Windows
•   Replace / Reflash Skylights in Band Room
•   Provide Air Conditioning for Server Room
•   Provide Sound System for Auditorium
•   Replace the Foot Bridges (only one being replaced)
•   Refinish Corridor Walls
•   Provide Storage Units w/Locks for Hallway on Second Floor of Gym
•   Provide Benches for Lobby
•   New Sign at Main Entrance
•   Add Tile to Corridor (added to project in addition to alternate work)


Bus Garage

•   Replace Roof
•   Add Emergency Lighting
•   Add Security System
•   Upgraded Phone System (Tied to District)
•   Add Water Softer System
•   Add Automatic Bus Wash